The first studies of the La Pedrera Reservoir began in September 1967 when the Centro de Estudios Hidrográficos (CEH) drew up a geological study regarding the viability of La Pedrera Reservoir. The latter was determined, but, for its construction, it would be necessary to solve a series of problems - and the need for deeper studies. New campaigns were carried out regarding the geological-geotechnical aspects and, in the month of March 1970, the Public Works Geological Service issued the Preliminary Report on the La Pedrera reservoir and works, next to Orihuela, Bigastro (Alicante). This report was more optimistic than the previous one, stating the viability of building the reservoir and hoping to evaluate, in an approximate way, the economic cost of the works for the correction of the land that would need to be carried out in the area of the left shoulder and the hills on the right bank.
The first project for La Pedrera Reservoir was approved on 2nd May 1973, and the bidding process was immediately opened for the competitive tendering. The works began in July 1973, and a term for completion of thirty six (36) months was established, having to be completed in August 1976. But things did not go as smoothly as initially planned and it was necessary to extend the term on four occasions:
The project approved in May 1973 would not be the final one since, during the course of the dam construction, it was necessary to process two Amended Projects and a Complementary Project.
Provisional acceptance of the works took place on 20th April 1983, while the provisional settlement was a month later, that is, in May 1983.
When the civil works were well under way, Project 03/77 on the Campo de Cartagena Canal Intake was implemented, dealing with the hydromechanical equipment which was going to be installed for the water intake. These works were adjudicated on 20th April 1978 with the term for completion being 5th January 1980. The works began on 4th July 1978 and they suffered a process similar to the strictly civil ones: three successive extensions in the term, an Amendment I, three price revision reports and a fourth extension for completion until 9th August 1981. This last term was met and the provisional acceptance took place on 8th February 1983 and the Act approved on 25th March 1983.
When the need arose to build La Pedrera dam, two places were studied regarding its possible location. The choice of the latter depended on a series of factors related with the geological-geotechnical nature of the substratum, the capacity of the reservoir being created, the dimensions of the dam and the viability and economic cost of the construction. The first place that was studied was the one that permitted greater reservoir capacity, which was located in the ravine situated in Arroyo Grande between Cabezo Gordo - left bank- and Cabezo del Moro, immediately downstream from its confluence with Rambla de Alcoriza. But the geotechnical conditions of the land ruled out this location. The geological evolution of the area had created an anticline of loamy material covered in clays coming from its decomposition, and protected by strata of softer rocks -limestone, conglomerates and sandstones – which had been levelled over the years, producing an inversion of the relief, in such a way that the loams of the storage area upstream of the dam are bordered by elevations of conglomerates and sandstones. These conglomerates transversely cross the first downstream boundary for the storage area proposed, and so their high permeability made it advisable to transfer the dam downstream, to Rambla de Alcoriza in the area formed by Cerro de La Pedrera and Cabezo del Moro that, although this would mean a reservoir of smaller capacity, would be sufficient, the permeability problems would be avoided and the length of the dam would be shortened.
The choice of the type of structure -concrete versus loose materials - was determined by the inadequacy of the loamy material -that loses its cohesive properties in contact with water - to support the loads transmitted by a concrete dam. Three alternative types of dams of loose materials were studied: homogeneous, rockfill with a central clay core and rockfill with facing. The final choice was the homogeneous dam due to the presence of quarries in the vicinity of the location -clays and bluish grey loams in the storage area upstream of the dam- and the non-existence of water in the immediate surroundings – necessary in great volumes for compacting the rockfill – and which would have to be transported from great distances.
The geographical environment of the reservoir is densely populated, and the nearest most important city is Orihuela, which is about 8 km away; it is about 20 km from Murcia capital following the route of the former Murcia to Alicante main road N-340a. The dam can be reached from Murcia following the road going from the right riverbank of the Segura river that connects the capital with Beniaján, Torreagüera, turning off at the Cabezo de la Plata signpost in the direction of Torremendo where, before reaching this municipality, a left turn must be taken to reach Dike III. The A-333 road runs along this dike leading to the main dam, Dikes I and II and to the Administration building. Another option is to continue through Zeneta until Hurchillo and from there to turn right to reach Dike III.
The nearest railway station is Orihuela, 8 km away, on the Cartagena-Alicante-Barcelona RENFE line.
The location of the reservoir can be seen in the following map:
LOCATION OF THE RESERVOIR
|
|
---|---|
Province
|
Alicante |
Municipality
|
Orihuela |
River
|
Rambla de Alcoriza |
Hydrographic basin
|
Segura |
DETAILS OF THE RIVER
|
|
Total Length from the top of the Cenajo watercourse to Segura river
|
6,0 km |
DETAILS OF THE BASIN
|
|
Surface area of La Pedrera reservoir basin
|
36,34 km² |
Maximum altitude of La Pedrera reservoir basin
|
300 m |
Shore length
|
31,00 km |
---|---|
Reservoir surface area
|
1272 ha |
Reservoir volume
|
246,90 hm³ |
BODY OF THE DAM
|
|
---|---|
Type
|
Loose Materials |
Old dam materials
|
Earth with clay core |
Upriver slope
|
3,5/1 (h/v) |
Downriver slope
|
3,0/1 (h/v) |
Height above course of river
|
61,30 m |
Level crest (axis of road)
|
111,30 m |
Crest length
|
716,00 m |
Crest width
|
9,00 m |
Total volume concrete
|
- |
Total volume of materials
|
5.547.000 m³ |
SPILLWAY
|
|
Number of spillways
|
None |
Type of spillway
|
- |
Situation
|
- |
Position relevant to flow direction
|
- |
Situation
|
- |
Closure type
|
- |
Number of openings
|
- |
Free length of each opening
|
- |
Total free legth
|
- |
Floodgate type
|
- |
La Pedrera Reservoir has the function of regulating part of the flows transported by the Left Bank Distribution Canal to meet the irrigation demands of Campo de Cartagena and to supply a series of towns and villages in its territorial environment, managed through the Mancomunidad de los Canales del Taibilla. Its reduced catchment area and its small flows would never have justified the construction of this reservoir, which is practically used as a regulating reservoir. It is a masterpiece of the distribution of the water coming from the Tagus-Segura Aqueduct through the Distribution Canals, and practically all its inflows come from the Tagus-Segura Joint Exploitation. This work started to take form during the I Economic and Social Development Plan (1964-67) –the beginning of the preliminary plan -, although it was not until the II Development Plan (1968-71) that it was finally defined technically and the works began, under the ministry of Federico Silva Muñoz.
In September 1967 La Pedrera Reservoir started to be studied in a regular way along with the Tagus-Segura Aqueduct. From the first moment this reservoir was assigned the function of being a regulating reservoir for the internal distribution of the water coming from the Tagus, for storing the volumes with which the Campo de Cartagena would be irrigated and for supplying a series of towns and villages of the Baja Vega del Segura, in the province of Alicante.
The main dam of La Pedrera is a gravity one, with a straight ground plan, and of earth construction with a clay core. The core is the impervious element, going from the foundations practically until the crest level, and it has slopes 1:1 upstream, and vertical downstream. From the inside to the outside, the dam is built of a clay core, two shoulders built with loams of the area, a transitional draining layer 2 m thick and a 4 m thick protective layer of rockfill -measured horizontally-.
The ground plan length of the dam is 716 m, its height from the foundations is 66.30 m, while on the bed it is 61.30 m. The volume of land with which the dam body was built is 5,547,000 cubic metres. To close the storage area upstream of the dam it was necessary to build three dikes, two of which are on the hills of the right riverbank and the third on the left.
View of the embankment of the main dam and Dike I from the right bank.
The cross-section of the dam is trapezoidal with slopes of 3.5:1 upstream and 3.0:1 downstream. The dam has it foundations at 45.00 –the bed is 50.00- according to a broken line that goes along the hillside of the natural downstream boundary for the storage area. The height of the crest of the main dam is 110.54 in the area of the abutments and 111.30 at the point half-way between both. It is 9 m wide distributed on a road of 6.0 m with two lanes and two verges measuring 1.50 m each.
The dam has a complex system of filters and drains built on both shoulders. In order to limit the interstitial pressures during the construction of the dam and when the drawoffs take place, the upstream shoulder was built with four horizontal drains, 1.20 m thick and consisting of two outer layers, 30 cm thick, of filtering material -sand -, and a central one of thicker material -gravels -, 60 cm thick.
On the other hand, when completing the vertical embankment of the clay core, on its downstream face, a vertical chimney drain was made, which goes along practically the whole height of the dam –up to the height of 103.00 - and continues horizontally from the level of the foundations until the end of the shoulder downstream. This chimney drain is made up of two outer layers of filtering material -sand - 1.50 m thick, which protect an inner layer, 4 m thick, consisting of gravels. Four horizontal drains are connected to this chimney drain and consist of a single layer of sand 30 cm thick. Finally, at the foundation level chimney drain is extended by means of a horizontal drain made up of a central layer -2.37 m thick - of rockfill, covered in two layers of filtering material -1.19 m thick – that, in turn, are each covered in a layer of sand – 1.50 m thick-. Outside the shoulder downstream, this filter finishes in a rockfill base that reaches a level of 55.00, on the lower berm of the dam.
The loams that make up the shoulder downstream are covered in a filtering layer -2 m thick measured horizontally- of gravels and a layer of rockfill, also 2 m thick measured horizontally. This shoulder presents two horizontal berms, the lower one located at 55.00 and 5 m wide, while the upper one is located at 88.10 and is 4 m wide.
La Pedrera Reservoir basin catchment area has a surface of 36.34 km² and its maximum height is 300 masl; it is completely within the province of Alicante, in an orographically uneven area, and whose natural flows are practically non-existent. The reservoir is located in the wadi called Rambla de Alcoriza and in order to build it, it was necessary to construct, apart from the main dam, three saddle dams at the sides in order to close off two water-courses located on the right bank -Dikes I and II - and a third on the left bank -Dike III -. The surface slope is of a markedly rectangular shape of about 8 km perpendicular to the dam and about 4.5 km parallel. This territory receives an average annual rainfall of about 275 mm.
The Normal Maximum Level of the reservoir that, due to the characteristics of the catchment area, does not have a spillway, is limited by the dam crest -height 110.50 -, and it is located at a height of 105.00. The total reservoir volume for the normal maximum level is 246.09 million cubic metres. On the other hand, the surface inundated for this level is 1,272 ha, the length of the shore, 31 km, and the length of the reservoir goes about 6 km up the wadi.
View of the reservoir, dam and intake tower from the right bank
La Pedrera dam and reservoir are located at the most eastern end of the Baetic Mountains. This area is formed by materials from the Tertiary period, from the Vindobonian age that were folded towards the end of the Helvetian age and during the Tortonian stage, in the middle of the Miocene period. The Miocene materials have been folded into steep dips, which in some cases are over 70º, amongst which we must highlight El Hurchillo anticline, whose north flank slopes down into the Segura trench.Here we find, in an almost vertical position, layers of sandstones and limestones.
From this anticline stretches a fold of a large radius that affects the Helvetian materials, which includes the materials of the storage area upstream the dam and the downstream boundary. Once the folding had taken place, a process of intense erosion began that broke up the calcareous roof –not very thick- of the anticline and produced the inversion of the relief by digging out a great hollow in the bluish-grey loams of the anticline core. In the next layer, corresponding to the Tortonian stage, starts the continental
Morphologically, the area of the reservoir can be described as a wide erosive depression surrounded by gentle reliefs that are somewhat higher on its northern side, due to the pronounced contrasts of its lithology. The great anticline, whose core is formed by loamy material from the Miocene protected with weak upper strata that are harder (sandstones, conglomerates and limestones), was eroded producing a wide valley or hollow that marks a great contrast in the relief. All the substratum of the area is formed by grey and blue loams from the Miocene that are very thick; in the reservoir basin these loams appear covered in greyish and brownish-grey clays with a high proportion of silt from the Quaternary period; it is about 12 m thick. To the sides of storage area upstream of the dam, the summit edges are made up of a mixture of loam-limestone and sandstones that, as they are more resistant to erosion, form the divide. These ridges are the remains of the broken cover of the anticline that produces gentle outward slopes, which are steeper toward the interior.
The strong erosion that took place in the bluish-grey loams led, in some cases, to the slipping of small scales of limestones that, on the one hand, ended up covering more recent layers of the Tortonian stage, as occurred on the south-eastern hillside of the Cabezo Gordo and, on the other, produced some gravity faults. Some slip faults were also produced between the limestones alternating with the bluish-grey loams, to the East and the South-east of the Cabezo del Moro. In short, the dam is located in the monocline series that closes the anticline on the North, while the storage area upstream the dam lies on the anticline core of bluish-grey loams that are impervious and which, only in the area of the natural downstream boundary for the storage area, the presence of Tortonian conglomerates gave rise to problems of imperviousness.
In order to determine the geological composition of the natural downstream boundaryfor the storage area, both of the main dam and the key dams, in 1971 the Public Works Geological Service (SGOPU) made twenty one (21) mechanical probings of lengths of between 15.5 m and 102.2 m and a total length of 1,128 m, distributed in the two axes which at that time were being considered as the possible location for the dam, and in the two hills of the right riverbank. These probings were supplemented with six electric probing profiles, with a total of 72 units. In each of the probings a pile, a surface nozzle and a stand pipe piezometer were placed, to measure the water levels. Below there is a description layers and the materials that appear in the studied environment, as contained in the SGOPU report in August 1971.
As a whole, a thickness of about 700 m was calculated for the Miocene period, of which 300 m corresponded to the Vindobonian age made up of loams, limestones, sandstones and pudding stone. The natural downstream boundary and the storage area ustream of the dam are entirely located in this formation and the following layers were defined:
As for the quarries where the various materials for the dam made of loose materials were to be obtained, it was advised that the rockfill should be from Helvetian light grey limestones, and the quarry chosen be in Cerro Gordo, also for the purpose of ruling out any later move. The report also proposed the use of conglomerates of the right bank that, in this way, would increase the stability of the right abutment, and clayey loams as the impervious nucleus.
The seismic activity of the area is very high and has intensity X on the MKS scale. Therefore, a horizontal seismic coefficient of 0.138 was adopted and a vertical one of 0.069 in contrast to the ones officially proposed of 0.1 and 0, respectively, for an earthquake with a 500 year return period.
La Pedrera dam and reservoir are located on the Servicio Geográfico del Ejército Maps 913 (27-36) Orihuela, 914 (28-36) Guardamar del Segura, 934 (27-37) Murcia and 935 (28-37) Torrevieja, on a scale of 1:50 000, published in 1997. The dam closes the Rambla de Alcoriza between El Cabezo del Moro on the right bank and El Cerro de La Pedrera on the left bank, about 400 m upriver from its confluence with Arroyo Grande, in turn, a tributary of the Segura river on the right bank. For the construction of the reservoir it was necessary to build, apart from the main dam located in the course of the wadi called Rambla de Alcoriza, three additional key dams.
The coordinates of the point where the Barran-co del Bosch meets the reservoir comes as follows:
Reference system ETRS89. Time zone= 30
X=686.400
Y=4.211.563
Geographical coordinates (based on the Greenwich meridian) :
X 2º 48’ 10” West
Y 38º 01’ 85” North